Two-Stage Design & Build: How to Maintain Cost Control and Competitive Tension

Two-stage Design & Build procurement, highlighting early contractor involvement, PCSA controls, competitive tendering, cost management and maintaining commercial control.

Two-stage Design & Build can be a great option when programme is tight, the design is still developing and early contractor input can improve delivery.

But there is a trade-off:

You appoint the contractor before you know the final price.

That can work extremely well, provided Stage 2 remains a controlled procurement exercise, rather than drifting into a negotiation with the preferred contractor.

The principle is simple:

Stage 1 selects the contractor. Stage 2 establishes the price.

So how do clients and project managers keep control?

1. Agree the rules at Stage 1

Use the competitive Stage 1 process to establish as much of the commercial framework as possible, including preliminaries, OH&P, PCSA deliverables, procurement procedures, risk principles and key contract terms.

Negotiate the rules while you still have leverage.

2. Make the Tender Event Schedule a key PCSA document

A robust Tender Event Schedule should set out how and when each major package will be procured.

For each package, track the design release, tender issue, return, review, recommendation and order dates.

This gives the client and PM visibility of whether procurement is genuinely progressing and, importantly, which parts of the forecast have actually been tested in the market.

3. Keep competition in the supply chain

The main contractor may no longer be competing, but the packages still can.

Agree appropriate tender lists, issue comparable information and interrogate the returns.

Don’t simply ask:

“Did we get three prices?”

Ask:

“Did three contractors price the same scope, programme and risk?“

That’s a much better test of competition.

4. Measure the contractor’s PCSA performance

A PCSA shouldn’t just be a period of time before entering the building contract.

Set meaningful KPIs and gateways around things such as:

  • tender events achieved;
  • design reviews completed;
  • procurement progress;
  • buildability input;
  • risk close-out;
  • programme development;
  • quality and timeliness of cost information; and
  • delivery of agreed PCSA actions.

If performance isn’t where it needs to be, the client should know before committing to the main contract.

5. Keep challenging the price

Don’t allow the contractor’s latest estimate to automatically become the budget.

Keep reconciling:

Cost Plan → Contractor Estimate → Tender Returns → Agreed Packages → Forecast Contract Sum

And ask:

How much of the forecast is agreed? How much is market-tested? How much is still provisional sums? What risks remain?

The quality of the number matters as much as the number itself. This is where an independent cost consultant will add genuine value.

6. Have a genuine back-up plan

This may be the most important control of all.

What happens if the price can’t be agreed? Or PCSA performance isn’t good enough? Or procurement isn’t delivering the required market evidence?

The back-up plan needs to be credible, not theoretical.

If everyone knows there is no realistic prospect of the contractor losing the project, the commercial dynamic inevitably changes.

Understand the alternative route before you need it.

The takeaway

Two-stage D&B isn’t about removing competition. It’s about moving it.

Once the main contractor has been selected, control comes from a strong Tender Event Schedule, competitive package procurement, independent cost challenge, measurable PCSA performance and a genuine back-up plan.

Two-stage D&B doesn’t create cost certainty by itself.

The controls around it do.

Links

Services – Comprehensive Director-Led Cost Consultancy

Developing a construction procurement strategy and selecting an appropriate route


Disclaimer: This article is for general information only and does not constitute professional, legal or contractual advice. Project-specific advice should always be obtained before making procurement or contractual decisions.

© 2026 EthosEQ Construction Advisors Ltd. All rights reserved.


Tags:

Colin Wood

Colin is a Partner & Managing Director of EthosEQ, a cost consultancy that helps occupiers, developers, and landlords across EMEA deliver high-quality, efficient, and brand-aligned spaces — while saving time and money. With 25 years of experience at leading global consultancies, Colin has worked with blue-chip clients to deliver over 5 million sq ft of office space in the past decade alone. Today, he leads a boutique, director-led firm that brings big consultancy expertise straight to clients — with more focus, flexibility, and care.